Delaware Avenue Complete Streets Project – Phase 2 Start Date 3/23
Delaware Avenue Complete Streets Project – Phase 2 Start Date 3/23
The Town’s contractor, Peter Luizzi & Bros. Contracting, has been back to work on Delaware Avenue the past two weeks completing the remaining Phase 1 waterline improvements. Phase 2 work will begin on Monday 3/23/26. Phase 2 work will be completed during daytime hours and will include intermittent lane closures throughout the day over the duration of this project.
Start of Phase 2 – Sidewalk, Roadway, and Complete Street Improvements
- Sidewalk
- Additional sidewalk added
- Existing sidewalk improved
- Accessibility improvements – curb ramps
- Roadway
- Grading and removal of old road surface
- New road surface/pavement
- Restriping of travel lanes
- Crosswalks
- Existing crosswalks refreshed
- Two crosswalks added across Delaware Ave at Salisbury and Grant
- Streetscape
- Improved Gateway at the Eastern Entrance to Bethlehem
- Landscaping along the corridor
Status of Phase 1 – Waterline Improvements Complete
- Waterline Installation Complete
- Snowden Avenue
- Lincoln Avenue
- Bedell Avenue
- Booth Road
- Plymouth Avenue
- Mason Road
- Elsmere Avenue
- Valve replacement or other Updates Complete
- Herrick Avenue
- Burhans Place
- Euclid Avenue (still in process)
- Normanskill Boulevard
- Delaware Plaza area
Stay Informed
The Town will provide regular updates through its website, email newsletter, and social media. Updates will include construction timing, traffic impacts, safety reminders, and progress photos.
- Weekly email updates, sign up here: http://eepurl.com/hzl9k5
- Project webpage: Delaware Avenue Complete Streets Project
- Facebook link: Delaware Avenue Complete Streets
- Instagram link: @DelAveCompleteSt